2/21/01
After a
short delay, the forms are removed from the pool and preparation
is made for the bottom floor.
2/9/01
The
concrete for the shell of the swimming pool, including the
cantilevered outlook, is complete.
2/2/01
Reinforcement
steel is being used to build swimming pool wall forms.
1/30/01
Glouster
Pierre and his crew are back to work, and can be seen here working
with the cement for the base of our swimming pool.
12/28/00
After
much red tape and an excellent job by our attorneys Jay Isherwood
and Pat Welcome, we settled with CZM and paid a fine so we could
return to work.
9/27/00
The
U.S. Virgin Islands Coastal Zone Management (CZM) required us to
stop working due to a problem with our permits.
9/22/00
Rock
infill to storm water discharge trench commenced.
9/15/00
Formwork
for footings is being positioned.
9/4/00
Ground
is broken for the foundation and the sewage system.
8/31/00
Clearing
the lot begins.
8/30/00
Behold
lot 121I LaValle B.C. (before construction).